Stanwell Park Public School Upgrade

Client: NSW School Infrastructure
Location: New South Wales
Project: Stanwell Park Public School Upgrade
Completion Date: September 2022
Completion Time: 15 Months
Value: $3.3m

Barpa has delivered a new multi-purpose hall at Stanwell Park Public School for NSW School Infrastructure.

The project involved the design completion and construction of a new multipurpose school building which included;
- Completion of concept design to Educational Facilities Standards & Guidelines requirements
- upgrade of site services and infrastructure including new pole mounted substation,
- landscaping works to the surrounding areas, and
- construction of new school hall comprising
 Canteen & Outside School Hours Care facility
 Male, female and accessible amenities
 Hall / presentation space
 Back of house and storages areas

With a total floor area of 325m2, the new Multipurpose Hall will provide a new and improved education facility to support the growing student community

Related Projects